News and Press Releases
Drilling Rig Arrives
November 8, 2007
Sefton Resources Inc announces that the drilling rig is now
in place at its wholly owned subsidiary TEG Oil & Gas USA well locations
at Tapia. It is anticipated that drilling at the Hartje 16 and Hartje 17 wells
ill be completed
by the end of the month, after taking into account rig-up and move time between
the wells.
Sefton also reports that TEG Oil & Gas USA has
successfully fired up the Clayton
Industries Steam Generator at Yule 7 and 10 well pads. Tests continue to check
that the control electronics and safety quipment are functioning properly.